Construction of the Kajaran-Agarak road section is in full swing – Road Department

Construction of the Kajaran-Agarak road section is in full swing – Road Department

ArmInfo.  Construction of the 32-kilometer Kajaran-Agarak road section, which is part of the “North-South” transport corridor, is proceeding at full pace. This is stated in a release by the “Road Department” Fund.

According to the source, this road is of strategic and economic importance. Its construction will significantly increase the volume of freight and passenger transportation, as well as the speed and comfort of traffic, which, in turn, will have a positive chain effect on other sectors of the economy.

The construction of the Kajaran-Agarak road section is one of the unique projects being implemented in Armenia, which simultaneously includes practically all road infrastructure: bridges, tunnels, overpasses, interchanges and other artificial structures.  A significant amount of work is also related to the relocation and construction of communication lines.

The overall physical progress of construction work currently stands at around 60%.  From a technical point of view, the most complex works have already reached a high percentage of completion.  For example, tunnel drilling has been fully completed, and more than 90% has already been completed of the earthworks in difficult terrain.

At this stage, interior lining and finishing works on the structures—bridges, retaining walls and tunnels—are continuing at a more active pace. On average, around 645 workers and 228 units of various construction equipment are involved in the construction work.

It should be recalled that the Kajaran-Agarak road is being constructed with co-financing from the Government of Armenia and the Eurasian Fund for Stabilization and Development. The project envisages the construction of 32 km of road, two tunnels and 17 bridges, the longest of which will be 720 m long.

 

The project contractor is a joint venture of Iranian companies—Abad Rahan Pars International Group and Tunnel Sadd Ariana. Technical supervision of the construction work is being carried out by the Croatian company Institute IGH, Joint-Stock Company for Research and Development in Civil Engineering. Back in April 2023, it became known that the Eurasian Fund for Stabilization and Development (EFSD) would provide Armenia with a $200 million loan for the construction of the fourth tranche of the “North-South” transport corridor. The route will be Category II and will bypass Meghri. It includes 5 interchanges, 2 tunnels (one of them approximately 450 m long, where final works on concreting the lining were underway in October 2026) and bridges. The planned commissioning of the section is in 2027.